New Construction of Rescue Coordination Centre, Landau
New construction of a rescue coordination centre in Landau (1,470,000 € total construction costs) with planning for an overall energetic concept, where waste heat from the technical control room will be used and where a new combined block heat and power plant will provide an emergency power supply.
About 450,000 € were used for the special technical equipment and components like a self-contained air-conditioning system and 2 cooling installations for the server rooms.
Important facts about the project
Services rendered |
|
Duration |
2008 - 2009 |
Investment |
1.500.000 Euro |
Client |
City of Landau, Building Management |