Final Audit of an Investment Program for the National Water Company in Mali
Final audit mission of the sectorial water programme II involving improvement measures of water supply systems of 14 production and distribution centres under management of "Energie du Mali S.A. (EdM)".
The programme assessed as final Audit had the goal to improve the operation of the water systems in all 14 secondary centres of the water operator company "Energie du Mali S.A. (EdM).
Important facts about the project
Services rendered |
The services of the consultant, directly hired by the funding agency KfW as external consultant, covered every aspect of operation and maintenance in the external centres of EDM excluding the capital Bamako. The objective was to know if the investments engaged were bringing the expected improvement of the water quality supplied and the supplying security for the population. |
Duration |
2002 |
Investment |
10.000.000 Euro |
Client |
Kreditanstalt für Wiederaufbau (KfW), Germany |